Parking Information for Toledo University | OH

Please remember that parking permits are required at all times including nights and weekends, in between semesters and academic breaks.
Please remember that parking permits are required at all times including nights and weekends, in between semesters and academic breaks.

Construction Soon Starting on Area 48

Construction Soon Starting on Area 48

Renovations on Area 48, which serves the Ruppert Health Center on The University of Toledo Health Science Campus, will begin on Tuesday, September 6.

The surface lot will be reconstructed from the ground up in three construction phases. Weather permitting, the parking area will reopen in late October.

During construction, the open section of Area 48 will be for patient parking only – staff will not be permitted to park in Area 48. All staff is encouraged to park in Area 43 or Area 46 throughout the duration of the construction project in Area 48.

Phase 1: Tentatively September 6th-26th

The East Vehicle Entrance off of Health Center Drive will be closed during Phase 1.

In the first phase of construction, The South (Door #5) entrance along with Door #3 & Door #4 (building exits) are to be used as emergency exits only.

The North (Door #1), East (Door #2) building entrances and Door #8 (building exits) will remain open during phase 1.

The West building entrance (Door #7) will remain unaffected during the construction project.

There will be a walking path (indicated in blue in above image) open during each phase of construction.

Phase 2A: Tentatively September 27th – October 7th

The second phase of construction will tentatively begin the last week of September.

While the North (Door #1) and East (Door #2) building entrances will remain open during phase 2A, the North (Door #1) building entrance will be utilized for pickup and dropoff only.

During phase 2A, the South (Door #5) entrance along with Door #3 & Door #4 (building exits) will reopen.

The East Vehicle Entrance off of Health Center Drive will also reopen.

The West building entrance (Door #7) will remain unaffected during the construction project.

There will be a walking path (indicated in blue in above image) open during each phase of construction.

 Phase 2B: Tentatively October 8th-21st

The renovation project will tentatively shift to phase 2B the second full week of October.

The North Vehicle Entrance off of Transverse Drive will be closed during phase 2B.

The North (Door #1) building entrance will also close during phase 2B.

All ambulances and transport vehicles will be directed to the East (Door #2) entrance for emergency calls entering the parking area from the East Vehicle Entrance off of Health Center Drive.

Door #8 (building exit) is to be used as an emergency exit only.

During phase 2B, the South (Door #5) entrance along with Door #3 & Door #4 will remain open.

The West building entrance (Door #7) will remain unaffected during the construction project.

There will be a walking path (indicated in blue in above image) open during each phase of construction.

All Ruppert Health Center staff are encouraged to park in Area 43, during construction all open spaces in Area 48 are reserved for patients.

All construction dates are subject to change.

Please remember all vehicles on campus must be registered with a permit purchased online in advance or by utilizing the ParkMobile App or a parking meter when visiting campus.

Updated parking policies and procedures do have parking permits enforced between semesters, during academic breaks and on weekends.

Permit Enforcement Hours:

  • Monday through Friday 7AM-10PM
  • Saturday & Sunday 9AM-5PM

On weekdays from 5PM-7AM and on Saturdays & Sundays, active permits may park in areas designated for other permits. Exceptions include: reserved, disabled, metered, patient and no overnight parking areas.